When must a mechanic's lien be filed in Mississippi?

Prepare for your Mississippi Business and Law Contractor Exam with flashcards and multiple-choice questions. Familiarize yourself with test strategies and understand complex concepts to excel on your exam!

In Mississippi, a mechanic's lien must be filed within 90 days of the last date that labor or materials were provided to the project. This requirement ensures that contractors, subcontractors, and suppliers have a defined timeframe during which they can assert their rights to secure payment for the work performed or materials supplied.

Filing the lien within 90 days is essential because it establishes a legal claim against the property for unpaid services or materials, allowing those who are owed money to seek recovery. The timeline emphasizes the importance of prompt action because delays can compromise the ability to secure the lien and, ultimately, payment.

Understanding this time limit is crucial for contractors and suppliers, as failure to file within this period can lead to losing the right to enforce their claim through a mechanic's lien. Thus, the 90-day timeframe acts as a protective measure for those in the construction industry, ensuring they have recourse in the event of non-payment.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy