What is a common cause for contract disputes in construction?

Prepare for your Mississippi Business and Law Contractor Exam with flashcards and multiple-choice questions. Familiarize yourself with test strategies and understand complex concepts to excel on your exam!

Misunderstanding of project specifications or change orders is a common cause for contract disputes in construction because these elements are critical to the execution of a project. When parties involved, such as contractors, subcontractors, and clients, have different interpretations of what the specifications entail or how change orders affect the scope of work, it can lead to significant disagreements. Miscommunications can occur regarding the quality of materials, deadlines, or expected outcomes, which ultimately create tension and potential conflicts. Ensuring clarity in these areas is vital for smooth project progression and avoiding disputes related to perceived failures to meet contractual obligations.

While the other factors, such as excessive costs of materials, long working hours, and unavailability of labor, can impact the overall management and financial aspects of a construction project, they generally do not directly lead to disputes the way misunderstandings of specifications and change orders do. These latter misunderstandings pertain to the core agreement and expectations set forth in the contract, making them a primary source of contention.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy